Weingart Center - Shelby Interim Housing Update

Posted on 02/14/2025

I am writing to provide you with a brief update on our efforts for the Shelby Interim Housing development located at 3340 Shelby drive.  Due to the recent fires, all projects were backed up with the City’s planning department which caused a delay in the start of construction.  However, WCA is back on track and moving forward.  Below is the schedule for construction and completion. 

  • General Contractor will mobilize the week of February 17th.
  • Roof demolition to begin week of April 2nd, installation to be complete week of April 15th.
  • Exterior demolition, excluding roof, to begin week of February 17th, to be completed week of March 17th. (the only significant item for this is the demolition of the balconies.)
  • Work on exterior common areas on National to start the last week of March.
  • Construction to be completed in mid-November 2025.

Additionally, WCA has hired APS Security, led by Vernon Rosado, to monitor the site now, during construction and once opened. 

Please share this information with your friends and neighbors.  And as always, please feel free to reach out to me with any questions.

Tonja Boykin
Chief Operating Officer
566 S. San Pedro St. Los Angeles CA 90013
phone: 213-689-2222 | Fax: 213-683-9912

[email protected] 

weingart.org

south robertson NC

© 2025 soronc.org.

Contact Us

310-295-9920

Social Media

Are you sure you want to remove this?

Please enter the email address you would like to send this to